Worcester & Birmingham Canal

Start date: October 22, 2021
End date: November 27, 2021
Planned Stoppages

Adjacent to University Station
Bridge 82, University Avenue

Update on 12/11/2021:

Due to specialist subcontractor availability, unfortunately, the canal wall repair works have been delayed by two weeks and subsequently extended the requirement for the cofferdam in the canal until week ending 26th November.

RESTRICTION (8am Monday 25 October until 5.30pm Monday 8 November 2021)

The navigation and towpath will remain open. Contractors working on behalf of Volker Fitzpatrick will install a fabric dam in offside of the canal to undertake bank protection works. Following the installation of the dam, works will start to install a new sheet piled canal wall. Buoys in the canal will create an exclusion zone around the dam and we kindly request boating customers to pass with caution.