Weaver Navigation

Start date: January 19, 2021

Est. end if know: March 20, 2021

Planned Stoppages

Barnton
Saltersford Large Lock

NAVIGATION CLOSURE (8am Monday 1 February until 4pm Friday 19 March 2021)

Update on 18/01/2021:

We have been reviewing the methodology for the renovation and repairs at Saltersford Lock.

Whilst this means we will be unable to start on site until 1st February, the programme of works will now be shorter than originally expected and we still anticipate re-opening the navigation, as planned, on 19th March.

We apologise for any inconvenience this delayed start may cause.