Trent & Mersey Canal

Start date: May 6, 2022
End date: May 21, 2022
Time: 12:00 am - 12:00 am
Planned Stoppages

Pipe Bridge, Etruria
Starts At: Bridge 119B Railway Bridge
Ends At: Bridge 119C Marconi Bridge
Up Stream Winding Hole: Above TM-058-003 Lock 40 Summit Lock at junction with Caldon Canal
Down Stream Winding Hole: Above TM-048-020 Lock 41, Plants Lock at junction with Macclesfield Canal

RESTRICTION (8am Monday 16 May until 6pm Friday 20 May 2022)

The navigation and towpath will be closed for up to 1 hour.

Third Party contractors will be removing the redundant Pipe Bridge. 

The bridge will be lifted out by crane and the canal and towpath will be closed for up to 1 hour during the lift.  

Warning signs, barriers and banksmen will be used. 

Please approach with caution and be prepared to stop when requested.

Works will only take 1 day to complete but this notice covers 5 days to give some flexibility in case the weather is not suitable for the crane lift.