Tame Valley Canal

Start date: May 7, 2022
End date: June 11, 2022
Time: 12:00 am - 12:00 am
Planned Stoppages

Goldshill Stop Railway Bridge
Up Stream Winding Hole: Ocker Hill Junction
Down Stream Winding Hole: Rushall Junction

TOWPATH CLOSURE (8am Monday 16 May until 6pm Friday 10 June 2022)

Midland Metro will be returning on site to complete works, following the installation of the new bridge deck.

The southern towpath will be restricted while brick repair works are completed.

On the 30th May, the southern towpath restriction will be removed and the northern towpath will be closed, with pontoons installed across half of the width of navigation until 10th June.

Access past the bridge will still be available on the southern towpath, and navigation traffic will be restricted to single lane traffic through the site.

Banksmen and signage will be utilised to manage canal traffic. We kindly remind boaters to take extra care when passing this section.