Stainforth & Keadby Canal

Start date: February 23, 2022
End date: April 7, 2022
Time: 12:00 am - 12:00 am
Planned Stoppages

Flap valve replacement
Bramwith Lock

ADVICE (8am Monday 21 March until 6pm Wednesday 6 April 2022)

Update on 14/03/2022:

These works have had further delays due to high water levels at the site. They will now start on the 21st March.

Update on 03/03/2022:

These works have been delayed, this is due to heavy rainfall in the area which would make the work more difficult to undertake. They are now due to start 14th March.

ADVICE (8am Monday 7 March until 6pm Sunday 27 March 2022)

Breheny Construction will be working on behalf of the Environment Agency undertaking flap valve replacement works to a culvert under the canal, this is to help protect against flooding.

No impact is expected to the public. All access to the culvert will be underneath and will not impact on the moorings area.