Planned Stoppages

Railway Bridge 129 Holmes Chord Refurbishment Works

Update on 23/02/2022:

This restriction is being removed as Network Rail has finished the works ahead of schedule.

RESTRICTION (8am Monday 18 October 2021 until 5pm Sunday 13 March 2022)

Contractors are repairing the railway Bridge and undertaking various different activities throughout the winter months which includes scaffolding and pontoons on the watercourse and towpath.

Skippers of all craft & towpath users may experience a delay of up to 20 minutes to enable the contractors to move the pontoons out of the way.

The towpath is to be kept open at all times during the works.