Canal Barrier between Rotherham Lock and Main St bridge
Starts At: Rotherham Lock Footbridge
Ends At: Main Street Bridge
RESTRICTION (8am Tuesday 2 August until 6pm Friday 5 August 2022)
Update on 21/07/2022:
Due to supplier delays this scheme has been put back by 1 week and will now start on the 2nd August and finish on and inclusive of 5th August.
RESTRICTION (8am Monday 25 July until 6pm Thursday 28 July 2022)
Please be advised that third party works on the flood barrier are taking place this will involve raising and lowering the barrier. Divers may be in the water.
Skippers of all craft are requested to slow down when approaching the site and be prepared to stop if requested. Delays of not more than 30 minutes may occur.