Rufford Branch (L&L Canal)

by

Start date: February 12, 2024
End date: March 8, 2024
Time: 12:00 am – 12:00 am
Planned Stoppages

Lock 4, Moss Lock
Up Stream Winding Hole: Bridge 1 Junction Bridge
Down Stream Winding Hole: Marsh Meadow Swing Bridge 6

NAVIGATION CLOSURE (8am Monday 12 February until 4pm Friday 8 March 2024)

The team scheduled to do this work at Lock 4, Rufford, are currently on site at Lock 3, Rufford.

The scope of the works at Lock 3 have increased from 10 metres of piles to 30 metres of piles plus backfill.

We envisage the work taking longer at Lock 3 thereby delaying the planned works at Lock 4, Rufford. We have considered deferring the second stoppage but believe its important to complete these works so we apologise to boating customers for any disruption caused.

The new closure dates for Lock 4, Moss Lock are 12 February 2024 to the 8 March 2024.