Stoppages & Restrictions

Starts At: Lock 65 Alfred Street
Ends At: Lock 80 Coal Pit Lower

Update on 26/01/2024:

Our Engineers have now completed the design phase and established a method of repair for the subsidence that’s taken place at Lock 67, Tannersfield Middle on the Rochdale Canal. 

We’re currently in the process of liaising with third party specialist contractors and ordering the necessary materials required to undertake the works.

Our contractors are scheduled to commence on site Tuesday 6 February.

We will provide a further update on progress by Friday 9 February.  