Planned Stoppages

Coppy Bridge, 57
Starts At: Bridge 56, Belfield Bridge
Ends At: Lock 50
Up Stream Winding Hole: Winding Hole, above Bridge 56, Belfield Bridge.
Down Stream Winding Hole: Turning Point just below lock 50.

NAVIGATION CLOSURE (8am Monday 20 February until 4pm Friday 17 March 2023)

Update on 02/02/2023:

We would like to update our customers that following additional investigations, it has been identified that the repairs work required are less complex than initially planned and therefore less time is required for these works.

The start date for this stoppage has been pushed back to 20/02/2023. The end date remains 17/03/2023.

Original message:

A stoppage is required to carry out repairs to Coppy bridge. 