River Nene

Start date: December 18, 2020

Est. end if know: May 1, 2021

Planned Stoppages

Chester Farm – new landing stage

Update on 15/02/2021:

These works will now be completed by 30 April 2021.

Update on 22/01/2021:

These works will now be completed between 4 January and 5 March 2021.

ADVICE (Monday 4 January until 5 February 2021)

DETAILS: Planned works will be taking place to create a new floating
landing stage on the River Nene at the following grid reference.

• Chester Farm SP 91862 67023

These works will now be completed between 4 January and 5 February 2021.

We request that boaters take heed of any signage or instructions from the
contractors on site. Please contact Tom Geddes at JBA Bentley on
tom.geddes@jba-bentley.co.uk or 01733 715960 for further information.