River Great Ouse

Start date: October 28, 2020

Est. end if know: March 13, 2021

Planned Stoppages

Various locations

Updated 24/02/2021:

NAVIGATION CLOSURE (until 12 March 2021)

Updated 16/02/2021:

Updated 01/02/2021:

NAVIGATION CLOSURE (Friday 19 November 2020 until 1 April 2021)

Our Winter Works Programme for 2020/2021 is a major investment in
many structures along the River Great Ouse, which will deliver
significant and long-term benefits to the navigation. However, in
order to deliver this, the closure of some locks will be longer than
usual and we apologise for any inconvenience this may cause.
Subject to weather and river conditions we aim that the river will be
fully open for navigation by Easter 2021.

 

LOCK FROM TO
Great Barford Lock COMPLETED
Godmanchester Lock CANCELLED
St Ives Lock 4 January – 12 March 2021
Brownshill Lock CANCELLED
Hermitage Lock 11 January – 12 March 2021