Regent’s Canal

Start date: April 16, 2021

Est. end if know: July 31, 2021

Planned Stoppages

Installation of scaffold overhanging the Regents Canal at 10 – 18 All Saints Street, Kings Cross
Starts At: Bridge 36, Maiden Lane Bridge (A5200)
Ends At: Bridge 37, Thornhill Bridge (A5203)

ADVICE (8am Monday 26 April until 6pm Friday 30 July 2021)

Scaffolding will be installed to allow works to take place at 10 – 18 All Saints Street, Kings Cross. This will overhang the off side of the Regents Canal by approximately 1m.
A temporary pontoon walkway will be installed under the scaffold to prevent boats coming into contact with the scaffold.
Please proceed with caution in this area.

 