Regent’s Canal

Start date: November 12, 2021
End date: November 25, 2021
Planned Stoppages

Towpath Closure
Starts At: Bridge 8, Charlbert Bridge
Ends At: Bridge 10, Primrose Hill Bridge

ADVICE (8am Monday 22 November until 6pm Wednesday 24 November 2021)

O’Connor Utilities Ltd have been commissioned to undertake maintenance works by National Grid to their underground apparatus.

A towpath closure will be in place to help facilitate the works; however, a minimal disruption diversion will be in place at the back of the towpath on The Royal Parks Land.

O’Connor will be working at x2 locations along the towpath, so the closure will be in place from Bridge 8, Charlbert Bridge to Bridge 10, Primrose Hill Bridge.

Navigation will always remain unrestricted.

Comments