Pocklington Canal

Start date: August 9, 2021

Est. end if know: September 17, 2021

Stoppages & Restrictions

Number 6 Swingbridge failure – Repairs needed

Update on 02/09/2021:

We are anticipating for the works to commence on the Monday 6th September and are expecting the repairs to be carried out within the week.

We will update the notice when we receive further information.

Update on 09/08/2021:

We have experienced delays sourcing the pintle and bearing and once received we anticipate that these works may take up to 4 weeks to be carried out.

We apologise for the inconvenience that this may be causing.

We will update the notice when we receive further information regarding the repairs.

Update on 09/07/2021:

We are still currently sourcing a new pintle and bearing and we anticipate that these works may take up to  4 weeks to be carried out.

Original message:

Engineers have attended to Number 6 swingbridge and have found the bearing to have failed. As such the bridge is unsafe to swing and navigation has been closed to prevent injury to anyone trying to operate the bridge.

A replacement part is currently being sourced and a programme developed to have the bearing replaced as soon as possible. Whilst the lead time on the replacement part is currently unknown we will provide a further update no later than Friday 9th July 2021.