Montgomery Canal

Start date: September 23, 2020

Est. end if know: March 1, 2021

Stoppages & Restrictions

Schoolhouse Bridge, Crickheath
Starts At: Bridge 85, Crickheath Heath Bridge
Ends At: Bridge 87, Waen Wen Bridge

Update on 05/11/2020:

Please note the revised end date of this notice: works are taking longer than planned to complete and the new end dates is 28th  February 2021.

ADVICE (8am Monday 14 September until 6pm Thursday 31 December 2020)

The navigation and towpath remain open. Montgomery Waterway Restoration Trust will be carrying out vegetation works and installing a temporary trackway as part of preparations to replace Schoolhouse Bridge.