Monmouthshire & Brecon Canal

Start date: March 5, 2022
End date: March 19, 2022
Time: 12:00 am - 12:00 am
Planned Stoppages

Lock 68, Toffs Lock, Llangynidr
Up Stream Winding Hole: Bridge 142
Down Stream Winding Hole: Below Lock 65

NAVIGATION CLOSURE (8am Monday 14 March until 4pm Friday 18 March 2022)

We have instructed contractors to carry out works at Lock 68 on the Monmouthshire & Brecon canal to help prevent leakage from the lock chamber. In order for this work to be completed quickly and effectively we need to ensure the lock is not used.

The contractors will be on site from Monday 14th March and will complete the works as soon as they are able, certainly by Friday 18th March.

The remainder of the lock flight will still be operational for smaller boats able to turn in the lock  pound. Please continue to book passage by calling 03030 404040 to help us ensure we can manage the water levels appropriately during this time.