Macclesfield Canal

Start date: October 1, 2020

Est. end if know: November 20, 2020

Planned Stoppages

Whitfield-Congleton 33kV replacement Aqueduct 7

Up Stream Winding Hole: Brook House
Down Stream Winding Hole: Congleton Golf Course

ADVICE (8am Monday 12 October until 5pm Friday 20 November 2020)

Please be advised Third party contractors will be onsite at Aqueduct 7 on the Macclesfield Canal to install a replacement electricity cable in the public footpath (Biddulph Valley Way), which passes under the canal at Aqueduct 7.
The canal and towpath will remain open but access to and from the towpath may be restricted.
We politely request all customers to approach the area with caution and be prepared to use another route if requested. Please listen to any advice that may be given by the third party contractors and take note of the signage onsite.