Llangollen Canal

by

Start date: December 6, 2023
End date: December 13, 2023
Time: 12:00 am – 12:00 am
Planned Stoppages

Starts At: Lock 2, New Marton Locks
Ends At: Lock 1, New Marton Locks

RESTRICTION (8am Wednesday 6 December until 4pm Wednesday 13 December 2023)

Update on 14/11/2023:

We apologise that the dates for this restriction have been revised.

We are having complications on site with land ownership, and this has resulted in the works being delayed by 3 weeks, the new dates are the 6 December 2023 through to the 13 December 2023.

RESTRICTION (8am Wednesday 15 November until 4pm Tuesday 21 November 2023)

Please be advised that third party contractors, Land and water services, will be working in this area from 15th November 2023 until 21st November 2023 to facilitate dredging works. They will be scraping out the sediment in Locks 1 and 2 to a point where there is space to load it into our hoppers. They will need to do this multiple times in order to clear as much sediment as possible.

Customers are able to navigate through this section once the dredger has moved out of the lock. They will endeavour to ensure any waiting time is kept to a minimum but please add on an estimated 1 hour extra to your journey.

Please note contractors will be operating Monday to Friday 7am – 6pm so there is free movement outside of this.

The Towpath will remain open for the duration of the works. 