Limehouse Cut

Start date: July 15, 2021

Est. end if know: September 14, 2021

Planned Stoppages

Installation of mooring walkway on the off-side of the canal approximately 200m long
Starts At: Bridge 3, Violet Road
Ends At: Bridge 4, Bow Common Lane

ADVICE (8am Monday 19 July 2021 until 6pm Monday 13 September 2021)

The width of the waterway will be reduced to a minimum of 9m to allow a pontoon based excavator and piling equipment to be used to install a new mooring walkway on the offside of the canal.
Please proceed with care on this section of waterway.
Pontoons to be craned in to Bow Free Wharf.