Leeds & Liverpool Canal

Start date: December 18, 2020

Est. end if know: January 30, 2021

Planned Stoppages

Bridge 1, Carolina St Changeline Bridge

RESTRICTION (8am Monday 11 January until 5pm Friday 29 January 2021)

Please be advised that Third party contractors will be onsite at Bridge 1, Changeline Bridge on the Leeds and Liverpool canal to paint a gas pipe crossing.
The third party contractors working for Cadent gas will be doing abrasive blasting of the pipe crossing followed by application of a 4-coat epoxy paint system. They will be working from a pontoon with scaffolding attached. There may a short delay for boaters until the pontoon and equipment are moved out of the way.
Whilst the navigation and towpath will remain open, we politely ask customers to approach the area with caution and listen to any advice that may be given by the third party contractors and be prepared to stop if necessary.