Leeds & Liverpool Canal

Start date: November 27, 2017

Est. end if know: March 17, 2018

Bridge 27A, Scarisbrick Bridge

RESTRICTION (Wednesday 29 November 2017 until Friday 16 March 2018)
THIRD PARTY WORKS

In order to facilitate bridge repairs, Scaffolding will be installed on Bridge 27a, Scarisbrick Bridge from 29 November 2017 to 16 February 2018.  The scaffold will create a width restriction at the bridge but boat traffic will not be adversely impacted with the exception of the following dates, where widebeam boats will not be able to pass:

4 to 18 December 2017
18 January to 1 February 2018
The towpath will also be diverted from 29 January to 16 February 2018.