Kennet & Avon Canal

by

Start date: January 29, 2024
End date: March 15, 2024
Time: 12:00 am – 12:00 am
Planned Stoppages

Limpley Stoke, Muir Woods (Winsley Bridge to Elbow Cottage)
Starts At: Bridge 175, Limpley Stoke Bridge
Ends At: Bridge 174 Winsley Bridge
Up Stream Winding Hole: Widbrook Winding Hole, upstream of bridge 170
Down Stream Winding Hole: KA-108-002, Avoncliffe Aqueduct

NAVIGATION CLOSURE (8am Monday 29 January until 4pm Friday 15 March 2024)

Work continues to mobilise contractors and equipment to the Limpley Stoke site, but as this began at short notice, our anticipated start date has unfortunately been deferred by one week to Monday 29th January 2024. Customers should be aware though, that an element of uncertainty remains, around the exact date.

We will continue to update this notice with further information as it becomes available.

You are welcome to contact us at [email protected] or 03030 404040 if you would like to discuss this information with the a member of our Customer Service Team

Original message:

Please be advised that a worsening leak, which we have been unable to resolve with water in the navigation, unfortunately means we must introduce an additional stoppage at Limpley Stoke, on the Kennet & Avon Canal. Temporary measures are already in place control the situation whilst our contractors mobilise, and we are striving for them to be on site by the end of January, 2024.

We expect the navigation to be closed for around 6 weeks, while we install dams, remove the water from the canal and effect the repairs. 

Our target for completion is 15th March 2024.

We will update this notice as the arrangements and programme develop. 