Huddersfield Broad Canal

Start date: December 17, 2021
End date: February 5, 2022
Stoppages & Restrictions

Starts At: Lock 7, Fieldhouse
Ends At: Lock 6, Riddings Lock
Up Stream Winding Hole: Winding Hole – Milnsbridge Marina
Down Stream Winding Hole: Winding hole – DS of Bridge 4, Railway

Update on 16/12/2021:

Unfortunately due to further works required, we have had to extend this stoppage.  The stoppage will be lifted as planned on 17/12/2021 for the Christmas period and then reinstated on 10/01/2022 until 04/02/2022.  We apologise for any inconvenience.

Original message:

A stoppage is required to carry out the following:

Lock 7 Fieldhouse, repairs to the cill.

Lock 6 Riddings Lock, repairs required as the planking hilti nails have corroded.