Stoppages & Restrictions

Top Gate, Uxbridge
Lock 88, Uxbridge Lock
Up Stream Winding Hole: Just above lock 88, Uxbridge lock
Down Stream Winding Hole: Just below lock 88, Uxbridge lock

NAVIGATION CLOSURE (8am Monday 29 January until 4pm Friday 1 March 2024)

Further investigations have identified more extensive brickwork repairs are required.

The delivery team have looked at several options to complete the works within the original schedule but this is now not possible due to overlapping activities which can’t be safely done concurrently and the time required for curing of the brickwork repairs.

Therefore a 2-week extension is required which means we will be on site from the 29 January through to the 1 March 2024.