Planned Stoppages

Replacement of off-side canal wall with sheet piling
Starts At: Bridge 200B, Gwr Bridge
Ends At: Bridge 200C, Nestles Bridge

ADVICE (7am Monday 29 January until 6pm Friday 19 April 2024)

Works are to dredge the canal bed to 1.2m depth, install sheet piling with back piles, backfill with concrete, install brick coper & recycled plastic fender. Silt curtain to be installed during dredging.