Calder & Hebble Navigation

Start date: August 7, 2020

Est. end if know: April 7, 2021

Stoppages & Restrictions

Flood Damage – Figure of Three locks
Starts At: Lock 24, Figure Of Three Bottom
Ends At: Lock 23, Figure Of Three Top

Update on 10/09/2020:

Following  substantial flood damage to Figure of Three locks in March, the towpath between Figure of Three Locks and Horbury Basin remains closed until further notice, to ensure the safety of the public.

The repairs to Figure of Three locks are likely to take until Spring 2021 to complete.

Once the repairs to the towpath side are complete at Figure of Three Locks it may be possible to open a safe route through the working area earlier than Spring 2021 and reopen the towpath

Navigation Closure

 

Update on 07/08/2020:

Our contractor, Kier, have started work on site.

They are currently installing a temporary access track to reach the damaged lock.

Update on 02/07/2020:

Work is progressing on engineering designs and permissions for the repairs to the flood damage.

Contractors Kier are planning to start work in July on installing access to the lock.

We anticipate that the repairs will take until Spring 2021 to complete.

Update on 26/03/2020:

Customers are asked to only move if essential to reach services and to follow government guidance at all times

Original message:

As a result of damage caused by Storm Ciara, Figure of Three locks will be closed for the foreseeable future.

Our teams are working to fully assess the damage caused and design a programme of works to bring the locks back into operation.

Our initial estimates are this may take up to a period of 12 months. We will provide further updates as our programme of works becomes clearer.

Comments

comments