Ashton Canal

Start date: November 12, 2020

Est. end if know: January 1, 2021

Stoppages & Restrictions

Lock 13, Crabtree Lane, Openshaw
Starts At: Bridge 21, Lumb Lane Bridge
Ends At: Lock 1
Up Stream Winding Hole: Lumb Lane, Bridge 21
Down Stream Winding Hole: Piccadilly/Dale Street Basin, Rochdale Canal

Update on 12/11/2020:

The third party contractor has confirmed their works by Lock 13 will no longer be carried out this winter. However, please be aware, the navigation remains closed due to other works in the area. Thank you.

Original message:

Third party contractors require a closure to remove a redundant gas pipe from a pipe bridge located at towpath level, and the underground element within the lock.

Comments

comments