Aire & Calder Navigation Main Line

by

Start date: May 30, 2022
End date: June 30, 2022
Time: 12:00 am – 12:00 am
Planned Stoppages

Ferrybridge Power Station Demolition Works – lifting pipe bridge
Synthetic Chemicals Bridge

RESTRICTION (8am Saturday 25 June until 6pm Wednesday 29 June 2022)

Update on 16/06/2022:

We have been advised of a change of date for this lift due to the police escort for the crane not being available for the previous given date.

RESTRICTION (8am Wednesday 8 June until 6pm Thursday 9 June 2022)

Contractors Keltbray are lifting a pipe bridge out from across the navigation, using a crane placed on the offside of the canal, as it is now redundant.

Can skippers of all craft please slow down when approaching the area and follow any instructions given by staff on site.

Delays of up to 20 minutes may be experienced.