Worcester & Birmingham Canal

by

Start date: October 20, 2022
End date: November 13, 2022
Time: 12:00 am – 12:00 am
Planned Stoppages

Gas pipe crossing just South of Bridge 57, Brockhill Lane
Bridge 57 Tardebigge-Old Wharf

ADVICE (8am Monday 31 October until 5pm Friday 11 November 2022)

Alfred Bagnall & Sons Limited on behalf of Cadent Gas will be repainting the gas pipe crossing the canal.

A fully encapsulated scaffolding will be erected across the canal and towpath to facilitate the works.  The towpath and navigation will remain open, although short delays may be encountered during the scaffolding erection and dismantling processes.  Towpath and navigation users will be safely managed through the works during these periods.