Grouting works from Bridge 3 to Bridge 4
Starts At: Longbottom Bridge
Ends At: Bridge 3, High Royd Bridge
Update on 21/09/2022:
A clay embankment is being built to prevent further leakage through the existing embankment. This has therefore extended the duration of the works.
We are hoping to have the works completed by and inclusive of Wednesday 28th September.
NAVIGATION CLOSURE (12.15pm Friday 16 September until 4pm Friday 23 September 2022)
The navigation between Bridge 3, High Royd Bridge and Bridge 4, Longbottom Bridge will be closed from today until Friday 23rd September, to carry out grouting repairs. This section will be dewatered to carry out the works with fabric dams in place.
We are looking for the works to be completed by Friday, but will update the notice after Tuesday, on how the works are progressing.