Hundred Foot Drain
TL 55598 96101 to TL 57205 98625 approx.
Update on 01/11/2023:
Further to Navigation Advisory Notice for the Hundred Foot Drain issued on 1 August 2023 this is now rescinded as the desilting works have been completed.
ADVICE (Tuesday 15 August until Tuesday 31 October 2023)
Desilting works will be taking place on the Hundred Foot Drain from 15 August
to 31 October 2023.
Work will be carried using land-based machines from Cradge Bank.
Project Contact: Matt Vyse – [email protected]