Peak Forest Canal

Start date: February 28, 2018

Est. end if know: May 31, 2018

Starts At: Lock 16
Ends At: Lock 1

Update on 16/05/2018:

Since the last update, the stone masons have made good progress in rebuilding the chamber wall, and are on track to finish all of the masonry work this week.  During the course of next week, the site team will re-install the lock gates and remove the scaffold and temporary dams in time to open by 5pm on 25th May.  There will be finishing works continuing over the following week, including the re-laying of the gate quadrants and landscaping works, so please following the direction of the site teams during that period.

Update on 18/04/2018:

Work to re-build the lock chamber wall at Marple Lock 15 have suffered a set-back this week after the brickwork exposed at the base of the lock wall was found to be in very poor condition.  It had been expected that the reconstructed masonry wall would be founded on top of the brickwork section of the wall, however this has not been possible and the wall has now been dismantled down to the invert of the lock. This marks a significant milestone in the project as we have now reached a stable foundation and the brickwork is being rebuilt currently.  Unfortunately this delay has meant that the planned opening date for 4 May is no longer achievable.  A revised schedule has now been developed and CRT anticipate navigation reopening on 25 May.

Update on 27/02/2018:

CRT wanted to update you on the latest progress on site at Marple and to advise you that unfortunately, the Marple Lock Flight will not be open in time for Easter.   It is now aimed to reopen the Marple Lock Flight in time for the May Day Bank Holiday (May 4).

At Lock 15 there have been issues while removing the stone from the towpath side lock chamber wall during the dismantling phase. Some of the stonework has started splitting and crumbling in parts and unfortunately, will not be able to reuse it as expected.  Working with the heritage advisor CRT have managed to source new replacement stone from a local quarry, but the need to have new stones cut and delivered has introduced the delay to reopening the navigation.

The rest of the works are progressing to plan.  They are currently excavating down to a depth of 7m behind the Lock wall and in the next few weeks will be installing the reinforcement steel cages and concreting behind the Lock wall ready for the rebuild.

The other maintenance works on the flight are progressing well too with new lock gates being fitted at Locks 1 and 13, a total of 10 locks have been grouted, large wash wall repairs between Lock 8 & Lock 9, Lock quadrant walls rebuilt and Lock slope towpaths upgraded. Volunteers are also doing a great job removing vegetation, installing new paddle gearing to the locks and fixing some of the towpath where it is in bad condition.

The new railings to Marple Aqueduct is on schedule. They are currently carrying out the ground works on site for the new railings to be installed w/c 27th February.

 

Comments

comments