Removal of life expired footbridge & installation of replacement structure
Bridge 153, Wharf Road Bridge
Update on 07/11/2022:
The works have now been completed ahead of the scheduled closing date.
RESTRICTION (8am Monday 17 October until 5pm Friday 11 November 2022)
Update on 03/10/2022:
Revised start date now confirmed as 17th October
Update on 28/09/2022:
Start date has been delayed due to overrunning associated utility works. Revised start date will be confirmed when available
Update on 13/09/2022:
Planned lifts will be occurring on the 5th and 6th of October with the 13th of October as a back-up. Short delays to onward journey to be expected. Local operatives will be able to advise further
RESTRICTION (8am Monday 3 October until 5pm Friday 28 October 2022)
The footbridge adjacent to Cropredy Rd Bridge (Br153) is being replaced. Navigation restriction in place during both removal and replacement. Dates/times for the two lifts tbc. Towpath closure in place with diversion over road via temporary pedestrian crossing for duration of works