Oxford Canal

by

Start date: September 23, 2022
End date: November 9, 2022
Time: 12:00 am – 12:00 am
Planned Stoppages

Removal of life expired footbridge & installation of replacement structure
Bridge 153, Wharf Road Bridge

Update on 07/11/2022:

The works have now been completed ahead of the scheduled closing date.

RESTRICTION (8am Monday 17 October until 5pm Friday 11 November 2022)

Update on 03/10/2022:

Revised start date now confirmed as 17th October

Update on 28/09/2022:

Start date has been delayed due to overrunning associated utility works. Revised start date will be confirmed when available

Update on 13/09/2022:

Planned lifts will be occurring on the 5th and 6th of October with the 13th of October as a back-up. Short delays to onward journey to be expected. Local operatives will be able to advise further

RESTRICTION (8am Monday 3 October until 5pm Friday 28 October 2022)

The footbridge adjacent to Cropredy Rd Bridge (Br153) is being replaced. Navigation restriction in place during both removal and replacement. Dates/times for the two lifts tbc. Towpath closure in place with diversion over road via temporary pedestrian crossing for duration of works