Oxford Canal

Start date: November 18, 2020

Est. end if know: November 28, 2020

Planned Stoppages

Bridge 14, Ansty Road

ADVICE (8am Wednesday 18 November until 6pm Friday 27 November 2020)

The navigation and towpath will remain open. Emergency works will be carried out to install a temporary scaffolding pipe bridge over the canal and towpath on the north side of Bridge 14 to carry a temporary pipe. The work will be halted as and when boats or towpath users require passage. We kindly ask customers to take extra care and follow directions when passing through the work area.