Towpath opposite annex building adjacent to Wolverhampton Mill Street Depot WV1 1LE
Starts At: Mill Street Bridge
Ends At: Horseley Fields Bridge
ADVICE (7am Monday 16 October until 6pm Friday 27 October 2023)
As part of survey works at the annex building adjacent to Wolverhampton Mill Street Depot, third party contractors will be taking samples of the towpath side retaining wall.
Temporary barriers and sandbags will be placed on the towpath around the works area. The towpath will remain open throughout the works and signage and banksmen will be used to manage traffic.
Works are planned to take place from 16/10/23 to 27/10/23, although access to the towpath to carry out works will be circa half-to-one day only.