Liverpool Link

Start date: September 24, 2021

Est. end if know: December 14, 2021

Planned Stoppages

Canning River Entrance and Albert Dock Gate, Liverpool South Docks
Starts At: Canning River Swing Bridge
Ends At: Salthouse Key Bridge

RESTRICTION (7am Monday 18 October until 5pm Monday 13 December 2021)

Update on 20/09/2021:

Due to unforeseen contractor delays, please note these works will now commence on Monday 18 October 2021, with a scheduled completion date of Monday 13 December 2021.

Whilst access will be maintained through the Albert Dock Gates to Liverpool South Docks, the Canning River Entrance will be out of use.

RESTRICTION (7am Thursday 7 October until 5pm Wednesday 24 November 2021)

Please be advised our team will be onsite to replace the Canning River Entrance powered bridges and Electrical Control Systems at Canning River Entrance and Albert Dock Gate, Liverpool South Docks.

Works will involve removing the existing control panels within the Canning Half Tide Control Building (North & South) as well as the MCU and installing new cables to assist with the panel upgrade. These works are required to maintain the safety and reliability of the assets.

Works will commence on 7 October 2021, with a scheduled completion date of 24 November 2021.

Whilst access will be maintained through the Albert Dock Gates to Liverpool South Docks, the Canning River Entrance will be out of use.