Lock 4, Saltford Lock
Update on 21/06/2021:
Please be advised that due to problems with the reinstallation of the gates these works have been delayed further.
We will issue a further update by 16:00 tomorrow.
Update on 14/06/2021:
Please be advised that due to delays caused today by third parties our mobilisation has been delayed as we now have to find another suitable cranage site and larger crane in order to lift the plant and equipment required for the works into the waterway.
It is anticipated that works will be completed by 12:00 on Monday 21st June.