South of Wykin Bridge 21
RESTRICTION (8am Monday 4 December 2023 until 6pm Saturday 6 January 2024)
A revised date of the 4th – 6th of December has been agreed for the third party contractors, DK Drainage Ltd, to replace an existing blocked pipe just south of Wykin Bridge 21.
The work will involve minor excavation and replacement of existing blocked pipework with HDPE pipework and finished to fit in with existing towpath.
Pedestrians may experience delays of up to 20 minutes, in order for the contractor to stop works and escort pedestrians through site.
Boaters are asked to proceed with care and follow any advice on site.