Grand Union Canal

by

Start date: January 22, 2024
End date: January 27, 2024
Time: 12:00 am – 12:00 am
Planned Stoppages

Basin adjacent to Lock 1, Camp Hill Top Lock, Birmingham
Starts At: Lock 1, Camp Hill Top Lock (Lock 52)
Ends At: Bridge 91, Jenkins Street

ADVICE (7am Monday 22 January until 6pm Saturday 27 January 2024)

Third party contractors are installing a porta dam at the basin adjacent to Lock 1, Camp Hill Top Lock to undertake an inspection of Bowyer Street Feeder Outlet. Navigation through the Lock will remain open as usual. Signage will be in place to make boaters aware of the porta dam. We kindly remind boaters to take care when passing through this area.