Embankment 39 Audley, near Blackburn
Starts At: Bridge 103, Cicely Bridge
Ends At: Bridge 102A, Audley Street Bridge
Up Stream Winding Hole: Winding Hole, Eanam Bridge
Down Stream Winding Hole: Winding Hole, Bower house fold bridge
RESTRICTION (8am Tuesday 2 January until 4pm Sunday 31 March 2024)
Following a review of project methodologies, we are pleased to advise these works can now be done as a restriction; a closure is no longer required, however we need to move the dates of these works. The new dates for the navigational restriction are 02 January 2024 through to the 31 March 2024.
Original message:
A stoppage is required to carry out some embankment repairs to stop leakage.