Start date: November 13, 2023
End date: December 6, 2023
Time: 12:00 am – 12:00 am
Stoppages & Restrictions

Fixed Weir 1, Welford Arm, downstream from Bridge 1, Leedhams Bridge, near Bosworth Mill Farm
Fixed Weir 1, Welford Arm O/S Br 1
Up Stream Winding Hole: Winding Hole 1, Clay Pit & Welford Clay Pit Marina Bridge
Down Stream Winding Hole: Winding Hole 8 & Bridge 52, Laughton Hills Bridge

NAVIGATION CLOSURE (until 4pm Wednesday 6 December 2023)

Update on 13/11/2023:

The towpath can now be open as we have all our equipment/materials on-site.

Original message:

A stoppage is required to carry out some crest leak and brickwork repairs. 