Start date: February 27, 2023
End date: March 12, 2023
Time: 12:00 am – 12:00 am
Stoppages & Restrictions

Weavers Bridge, 65
Starts At: Bridge 64, Arley Bridge
Ends At: Bridge 66, Aberdeen Bridge
Up Stream Winding Hole: Turning Point, above White Bear Bridge 69.
Down Stream Winding Hole: Winding Hole at Bridge 60A, Wigan Rowing Club Bridge.

TOWPATH CLOSURE (until 4pm Friday 10 March 2023)

Update on 27/02/2023:

We would like to advise our customers that our in-water works have been completed and the navigation is now open. Please note that the towpath will need to remain closed until the published end date which is 10/03/2023.

Original message:

A stoppage is required to carry out repairs to the towpath support beam.  