Mepal Pumping Station – TL 44029 8134
What3Words – Conspire.flexed.petrified
RESTRICTION (Wednesday 5 October until Wednesday 12 October 2022)
Please be advised works to provide a new ultrasonic gauging station at Mepal will commence adjacent to the Mepal Bridge on 5 October 2022 for 1 week. The gauging station will be made up of 2 transducer racks
installed on either side of the banks on the New Bedford River. These racks will sit on piles which will be driven into the bank using a pontoon mounted piling rig no larger than 13.65m by 6.3m thereby reducing the width of the channel in this area.
Please take care when navigating in this area and adhere to any signage or instructions from the contractors on
site.