Birmingham & Fazeley Canal

by

Start date: August 12, 2022
End date: August 24, 2022
Time: 12:00 am – 12:00 am
Planned Stoppages

Starts At: Lock 5, Curdworth
Ends At: Lock 6, Curdworth
Up Stream Winding Hole: Curdworth Top Lock
Down Stream Winding Hole: Curdworth Bottom Lock

NAVIGATION CLOSURE (9pm Monday 22 August until 6am Tuesday 23 August 2022)

BBV, a contractor working on behalf of HS2, are commissioning a Dive Survey to assess the condition of the canal walls and bed between Locks 5 and 6 prior to carrying out any construction works on the North side. 

The survey will take place overnight for 1 night. 

The navigation and towpath will be closed affecting boater and towpath customers.