Sheffield & South Yorkshire Navigations

Start date: March 9, 2021

Est. end if know: May 24, 2021

Planned Stoppages

Strawberry Island Emergency Bank Slippage Repairs
Strawberry Island Bridge 73B

Update on 20/04/2021:

Due to further findings the repair works will continue until the 23rd of May.

RESTRICTION (8am Monday 29 March until 6pm Sunday 16 May 2021)

Update on 18/03/2021:

The works will now commence on the 29th of March due to delays in mobilising the pontoon.

RESTRICTION (8am Monday 22 March until 6pm Sunday 9 May 2021)

Contractors will be undertaking bank slippage repairs on the bank of the River Don on the other side of the island, on behalf of the Environment Agency.
Narrowboats and small vessels will be able to pass through next to the pontoon on the east side of the navigation.
Any larger vessels should contact Liam Gallagher from BAM Nuttall on 07776 680412 as far in advance as possible to discuss the possibility of navigating past the works.