River Wissey

Start date: January 7, 2022
End date: April 7, 2022
Time: 12:00 am - 12:00 am
Planned Stoppages

Nr Hilgay Bridge – National Grid Reference:
TL 62075 98755

ADVICE (Thursday 10 February until 6 April 2022)

Further to our navigation advisory notice issued on 6 Dec 2021, we can
confirm contractors have commenced their work to replace sheet piling
approximately 10m to the east of Hilgay Bridge. Please be aware of the
location of the work barge being used.

Navigation is still possible but on a single file basis. Boaters are requested to
proceed with extreme caution and take heed of any signage and instructions
from the contractors on site.

Original message

Please be aware, contractors are carrying out replacement piling works
approximately 10m to the east of the bridge that carries Bridge Street over
the river Wissey between 10 January 2022 & 6 April 2022.

If navigating in this area please proceed with caution and take heed of any
signage and instructions from the contractors on site.