River Great Ouse/Little Ouse

Start date: August 19, 2021

Est. end if know: September 18, 2021

Stoppages & Restrictions

Little Ouse Railway Bridge – Brandon
Grid Reference: TL 7670 87143
What3Words: urgent.crispier.asterisk

RESTRICTION (Monday 23 August until Friday 17 September 2021)

Please be aware contractors working on behalf of Network Rail will be undertaking
some urgent health and safety repairs to Little Ouse Railway Bridge. This will
necessitate scaffolding being constructed under the bridge, which will reduce
headroom by no more than approximately 300mm when in place.

A temporary, floating pontoon will be used to erect/dismantle the scaffolding. This
will be moved to allow boaters to navigate through, however river users are advised
that short delays of up to 30 minutes may be experienced.

Please take care when navigating in this area and adhere to any signage or
instructions from the contractors on site.

Comments

comments