Northampton Arm (Grand Union Canal)

Start date: January 8, 2021

Est. end if know: February 13, 2021

Planned Stoppages

Lock 15, near Briar Hill

Starts At: Lock 1
Ends At: Lock 16
Up Stream Winding Hole: Downstream of Lock 1
Down Stream Winding Hole: Northampton Bottom Lock 17

Update on 19/01/2021:

Please note the navigation will be closed at Lock 1 and Lock 16 for the duration of the gate replacement works at Lock 15.

 

NAVIGATION CLOSURE (8am Monday 18 January until 4pm Friday 12 February 2021)

Update on 22/12/2020:

Unfortunately, our programme has been affected due to some of our construction team having to self-isolate.  As a result, we will not be able to complete all the pre-Christmas preparation for the stoppage at Lock 15, including moving plant and equipment to site.

We therefore need to delay the navigation closure by one week.  This will now start on 18th January 2021 and re-open on 12th February 2021.

Original message:

A stoppage is required to enable the replacement of the top gate.