Liverpool Link

Start date: November 25, 2021
End date: December 14, 2021
Stoppages & Restrictions

Albert Dock Gate
Albert Dock Hartley Bridge

RESTRICTION (8am Wednesday 24 November until 5pm Monday 13 December 2021)

Please be advised that our contractors will be onsite at the Albert Dock Gate at Salthouse Quay to upgrade the control functions of the Liverpool Gate control system.   

Our contractors will erect scaffolding as a working platform on either side of Hartley bridge into the dock to assist with replacing parts on the side of the bridge. The scaffolding will be installed 1.5m off the edge of the bridge on either side reducing the opening beneath the bridge from 10m to 7m. 

Although the navigation will remain open, we politely ask customers to approach the area with caution, take note of any signage and listen to any advice that may be given by our contractors. 